Earned Value Management Calculator

Calculate cost and schedule variances and performance indices from earned value, actual cost and planned value.

Cost variance

20.00money
Schedule variance
-30.00 money
Cost performance index
1.2 ratio
Schedule performance index
0.8 ratio

Formula

CV = EV − AC; SV = EV − PV; CPI = EV/AC; SPI = EV/PV.

Cost variance ≈ (120)-(100) · Schedule variance ≈ (120)-(150) · Cost performance index ≈ (120)÷(100) · Schedule performance index ≈ (120)÷(150)

How to use

  1. Enter earned value at the reporting date.
  2. Enter actual cost and planned value at the same date.
  3. Read cost and schedule variances and indices.

Examples

  • EV 120, AC 100 and PV 150 give CPI 1.2 and SPI 0.8.

Frequently asked questions

What is earned value?

The budgeted cost of work actually completed.

Is schedule variance measured in days?

No. It is expressed in the same monetary units as planned value.

What does an index below one mean?

CPI below one indicates cost overrun; SPI below one indicates less work earned than planned.