High-Low Method Calculator
Estimate variable cost per unit, fixed cost and total cost from the highest and lowest activity observations.
Formula
v=(CH−CL)/(QH−QL); F=CL−v×QL; C=F+v×Q.
Variable cost per unit ≈ ((1,500)-(1,000))÷((200)-(100)) · Fixed cost ≈ (1,000)-(5)×(100) · Estimated total cost ≈ (500)+(5)×(150)
How to use
- Enter the highest and lowest activity levels.
- Enter their matching costs in one currency.
- Set target activity and read the estimates.
Examples
- Activity 100/200 with costs 1000/1500 gives v=5 and F=500.
Frequently asked questions
Which observations should I use?
Choose activity extremes, not cost extremes; the two activity levels must differ.
Is this a regression?
No. Only two observations determine this linear estimate.
Can I extrapolate?
Use the relevant operating range; unusual observations can distort the estimate.