KiloAtlas
EN
EnglishBahasa IndonesiaTiếng Việt

High-Low Method Calculator

Estimate variable cost per unit, fixed cost and total cost from the highest and lowest activity observations.

Variable cost per unit

5
Fixed cost
500.00
Estimated total cost
1,250.00

Formula

v=(CH−CL)/(QH−QL); F=CL−v×QL; C=F+v×Q.

Variable cost per unit ≈ ((1,500)-(1,000))÷((200)-(100)) · Fixed cost ≈ (1,000)-(5)×(100) · Estimated total cost ≈ (500)+(5)×(150)

How to use

  1. Enter the highest and lowest activity levels.
  2. Enter their matching costs in one currency.
  3. Set target activity and read the estimates.

Examples

  • Activity 100/200 with costs 1000/1500 gives v=5 and F=500.

Frequently asked questions

Which observations should I use?

Choose activity extremes, not cost extremes; the two activity levels must differ.

Is this a regression?

No. Only two observations determine this linear estimate.

Can I extrapolate?

Use the relevant operating range; unusual observations can distort the estimate.

Sources

Updated:

Related tools

Search conversion tools