PERT Calculator

Estimate one activity duration, standard deviation and variance using the three-point PERT approximation.

Expected duration

5days
Standard deviation
1 days
Variance
1 days²

Formula

E=(O+4M+P)/6; σ=(P−O)/6; variance=σ².

Expected duration ≈ ((2)+4×(5)+(8))÷6+0×sqrt((5)-(2))+0×sqrt((8)-(5)) · Standard deviation ≈ ((8)-(2))÷6 · Variance ≈ (1)^2

How to use

  1. Enter the optimistic duration.
  2. Enter the most likely and pessimistic durations in days.
  3. Read the PERT mean and spread.

Examples

  • Estimates 2, 5 and 8 days give mean 5 days and standard deviation 1 day.

Frequently asked questions

Which order is required?

Use optimistic ≤ most likely ≤ pessimistic.

Is this a completion guarantee?

No. PERT gives a model estimate from your three inputs.

Does this solve a project network?

No. These results describe a single activity.