PERT Calculator
Estimate one activity duration, standard deviation and variance using the three-point PERT approximation.
Formula
E=(O+4M+P)/6; σ=(P−O)/6; variance=σ².
Expected duration ≈ ((2)+4×(5)+(8))÷6+0×sqrt((5)-(2))+0×sqrt((8)-(5)) · Standard deviation ≈ ((8)-(2))÷6 · Variance ≈ (1)^2
How to use
- Enter the optimistic duration.
- Enter the most likely and pessimistic durations in days.
- Read the PERT mean and spread.
Examples
- Estimates 2, 5 and 8 days give mean 5 days and standard deviation 1 day.
Frequently asked questions
Which order is required?
Use optimistic ≤ most likely ≤ pessimistic.
Is this a completion guarantee?
No. PERT gives a model estimate from your three inputs.
Does this solve a project network?
No. These results describe a single activity.