KiloAtlas
EN
EnglishBahasa IndonesiaTiếng Việt

Takt Time Calculator

Calculate the production pace needed to meet customer demand from net available time and required units.

Takt in minutes

2min/unit
Takt in seconds
120 s/unit
Required hourly rate
30 units/h

Formula

Takt time = net available production time / customer demand.

Takt in minutes ≈ (420)÷(210) · Takt in seconds ≈ 60×(2) · Required hourly rate ≈ 60÷(2)

How to use

  1. Enter net available production minutes for a period.
  2. Enter customer demand for the same period.
  3. Read the target time per unit and hourly rate.

Examples

  • 420 available minutes and 210 required units give 2 minutes per unit.

Frequently asked questions

Is takt the measured cycle time?

No. Takt is a demand target; cycle time is observed production time per unit.

Should I subtract breaks?

Use net time after planned nonproduction time, consistently for the chosen period.

Does takt include defect allowance?

No. The demand input represents required good units; capacity planning needs separate loss assumptions.