Takt Time Calculator
Calculate the production pace needed to meet customer demand from net available time and required units.
Formula
Takt time = net available production time / customer demand.
Takt in minutes ≈ (420)÷(210) · Takt in seconds ≈ 60×(2) · Required hourly rate ≈ 60÷(2)
How to use
- Enter net available production minutes for a period.
- Enter customer demand for the same period.
- Read the target time per unit and hourly rate.
Examples
- 420 available minutes and 210 required units give 2 minutes per unit.
Frequently asked questions
Is takt the measured cycle time?
No. Takt is a demand target; cycle time is observed production time per unit.
Should I subtract breaks?
Use net time after planned nonproduction time, consistently for the chosen period.
Does takt include defect allowance?
No. The demand input represents required good units; capacity planning needs separate loss assumptions.
Sources
Updated: